Apr 10

Calendar Risk Modelling in Safran Risk: GCC Heat, Ramadan, and Weather Disruptions

ADNOC announced a $150 billion capital investment plan through 2030, making it one of the largest sustained construction programmes in the world. The scope spans upstream developments (Hail and Ghasha, Lower Zakum expansion, SARB Deep Gas), midstream infrastructure (gas processing, NGL pipelines), downstream expansions (Ruwais refinery, TA'ZIZ petrochemicals), and the massive Ras Al Hekma coastal development. Across this portfolio, thousands of construction activities are affected by environmental conditions that are unique to the Gulf Cooperation Council region: extreme summer heat that forces outdoor work bans, Ramadan-reduced working hours, sandstorms that halt operations without warning, and public holidays that vary by emirate. These are not minor productivity adjustments. On a $150 billion programme, calendar risks collectively drive more schedule variability than most technical risks on the register.

Calendar risk modelling in Safran Risk is the practice of using Poisson frequency distributions to generate probabilistic non-working days within a Monte Carlo simulation. Unlike deterministic approaches that block fixed calendar periods, calendar risk modelling treats disruptions as stochastic events that vary in frequency and duration across each simulation iteration. This produces a more realistic S-curve that reflects the true variability of GCC construction schedules.

Most project teams in the GCC handle environmental disruptions by reducing productivity factors in their P6 calendars: 80 percent productivity in summer, 90 percent during Ramadan. This approach is fundamentally flawed because it treats variable events as constants. Some summers are worse than others. Some Ramadan periods coincide with peak summer heat (as the Islamic calendar shifts relative to the Gregorian calendar), compounding the impact. Sandstorms are inherently unpredictable. A QSRA that does not model these as probabilistic calendar risks will produce an S-curve that understates the true schedule exposure.

This article explains how to model calendar risks in Safran Risk for GCC construction projects, using ADNOC’s $150 billion capital programme as the context for practical examples.


What Is Calendar Risk and Why Does It Matter in the GCC?

Calendar risk refers to any disruption that removes working days from the project schedule due to environmental, regulatory, or cultural factors. In the GCC, these disruptions are frequent, impactful, and variable. A project that ignores calendar risk and relies on deterministic productivity adjustments will systematically underestimate its schedule exposure. For the complete QSRA methodology that provides the framework for integrating calendar risks with duration uncertainties and discrete risk events, see Schedule Risk Analysis (QSRA): Guide to Monte Carlo + Examples.

In Safran Risk, calendar risks are modelled using a Poisson distribution that generates a random number of non-working days per activity or calendar period in each Monte Carlo iteration. The analyst defines the mean frequency (lambda), and the simulation samples a different number of disruption days each time, creating realistic schedule variability that deterministic calendars cannot capture.


GCC-Specific Calendar Risk Categories

Each calendar risk category requires a different modelling approach in Safran Risk. The following categories cover the primary sources of calendar disruption across ADNOC’s project portfolio and GCC construction more broadly.

Extreme summer heat (June to September) triggers mandatory outdoor work bans under UAE labour law when temperatures exceed 50 degrees Celsius during midday hours. The number of lost working hours varies by year, by location (coastal vs inland), and by trade (welding is more heat-sensitive than electrical work). IQRM models this as a Poisson distribution with a mean of 15 to 25 lost days per summer, applied to outdoor activities only. Indoor activities (fabrication shops, control room fit-out) receive a lower mean of 3 to 5 lost days for indirect heat effects.

Ramadan reduced working hours affect labour productivity across all trades for approximately 30 days per year. The productivity impact varies by workforce composition (Muslim vs non-Muslim crew ratios), by trade (physically demanding trades are more affected), and by whether Ramadan falls during summer (compounding heat effects) or winter. IQRM models Ramadan as a Poisson distribution with a mean of 8 to 12 equivalent lost days, applied to all labour-intensive activities.

Sandstorms (shamal winds) halt all outdoor operations, restrict material deliveries, and can damage exposed equipment. The frequency varies by season and location: the shamal season (March to August) brings more frequent events in Abu Dhabi’s western region than in Dubai. IQRM models sandstorms as a Poisson distribution with a mean of 5 to 10 disruption days per year for exposed sites, applied to outdoor activities and logistics-dependent activities.

Public holidays and national events vary by GCC country and can include unscheduled additions for national celebrations. The UAE typically has 10 to 12 public holidays per year, but additional days may be declared for events such as national anniversaries or sporting events. IQRM models this as a uniform distribution of 10 to 15 non-working days per year.


Configuring Calendar Risks in Safran Risk: Step by Step

Safran Risk’s calendar risk engine allows the analyst to define disruption events with a frequency distribution and assign them to specific activity calendars. The simulation generates a different number of non-working days in each iteration, creating the schedule variability that deterministic calendars cannot capture.

Calendar Risk Distribution Mean Lost Days/Year Applied To
Summer heat (outdoor) Poisson (lambda = 20) 15-25 All outdoor construction activities
Summer heat (indoor) Poisson (lambda = 4) 3-5 Fabrication, indoor fit-out
Ramadan Poisson (lambda = 10) 8-12 All labour-intensive activities
Sandstorms Poisson (lambda = 7) 5-10 Outdoor and logistics-dependent
Public holidays Uniform (10, 15) 10-15 All activities

Total Calendar Risk Exposure (outdoor) = Summer Heat + Ramadan + Sandstorms + Public Holidays

ADNOC example: 20 + 10 + 7 + 12 = 49 mean lost days/year. On a 4-year programme, that is 196 lost days (approximately 10 months) of schedule variability that deterministic calendars treat as zero.


The Compound Effect: When Ramadan Falls in Summer

The Islamic calendar shifts approximately 11 days earlier each Gregorian year. When Ramadan coincides with peak summer (as it did from 2013-2018 and will again in the early 2030s), the productivity impacts compound. Workers observing the fast in 50-degree heat have significantly reduced physical capacity. The combined effect of Ramadan plus summer heat is not additive; it is multiplicative. IQRM recommends modelling this compound scenario as a separate calendar risk with a higher Poisson lambda (mean 30 to 35 lost days) applied during years when Ramadan falls between June and August. For understanding how these calendar risks feed into the overall S-curve and confidence levels, see P50, P80, P90 Confidence Levels in Risk Analysis.


Best Practices for Calendar Risk Modelling in the GCC

First, never use deterministic productivity deductions as a substitute for probabilistic calendar risk modelling. A flat “80 percent summer productivity” factor produces the same schedule impact in every Monte Carlo iteration and eliminates the variability that makes QSRA valuable. Use Poisson distributions in Safran Risk’s calendar risk engine instead.

Second, differentiate calendar risks by activity type. Outdoor civil works, indoor fit-out, commissioning, and logistics-dependent activities have different vulnerability profiles. Applying the same calendar risk to all activities overstates the impact on indoor work and understates it on exposed outdoor work.

Third, calibrate Poisson parameters using local weather records. Abu Dhabi Meteorological Centre publishes historical data on extreme heat days, sandstorm events, and humidity levels. Using 10 years of local data to set the lambda parameter produces more credible results than using generic GCC assumptions. For how tornado charts reveal which calendar risks drive the most schedule impact, see Sensitivity Analysis in Schedule Risk: Tornado Charts and Risk Drivers.

Fourth, model the Ramadan-summer compound effect separately. When Ramadan falls during peak summer months, the combined impact exceeds the sum of individual effects. Create a conditional calendar risk scenario in Safran Risk that applies the higher compound lambda during the relevant years of the project duration.


Frequently Asked Questions

What is calendar risk in schedule risk analysis?

Calendar risk refers to any disruption that removes working days from the project schedule due to environmental, regulatory, or cultural factors. In GCC construction, the primary calendar risks are extreme summer heat, Ramadan-reduced working hours, sandstorms, and public holidays. These are modelled using Poisson distributions in Safran Risk rather than deterministic calendar adjustments.

How does Safran Risk model calendar risks?

Safran Risk uses a Poisson distribution to generate a random number of non-working days per activity or calendar period in each Monte Carlo iteration. The analyst defines the mean frequency (lambda), and the simulation samples a different number of disruption days each time, creating realistic schedule variability that deterministic calendars cannot capture.

Why is a Poisson distribution used for calendar risks instead of a fixed number?

A fixed number produces the same schedule impact in every Monte Carlo iteration, eliminating the variability that makes QSRA valuable. A Poisson distribution reflects reality: some summers are hotter than others, some years have more sandstorms, and Ramadan’s impact varies with workforce composition. The distribution generates different disruption counts per iteration, producing a realistic S-curve.

How many working days does summer heat cost on GCC construction projects?

IQRM models extreme summer heat as a Poisson distribution with a mean of 15 to 25 lost days per year for outdoor activities and 3 to 5 lost days for indoor activities. The exact parameters should be calibrated using local meteorological data. Over a 4-year programme, outdoor calendar risk alone can generate approximately 10 months of schedule variability.

What happens when Ramadan falls during summer in the GCC?

The impacts compound multiplicatively, not additively. Workers fasting in 50-degree heat have significantly reduced physical capacity. IQRM recommends modelling this as a separate compound calendar risk with a higher Poisson lambda of 30 to 35 lost days during years when Ramadan coincides with June through August.

What is ADNOC’s $150 billion capital programme?

ADNOC has committed $150 billion in capital investment through 2030 across upstream (Hail and Ghasha, Lower Zakum, SARB Deep Gas), midstream (gas processing, NGL pipelines), downstream (Ruwais refinery, TA’ZIZ petrochemicals), and the Ras Al Hekma coastal development. It represents one of the largest sustained construction programmes globally.


IQRM delivers specialist training and consulting in Safran Risk, calendar risk modelling, and quantitative schedule risk analysis for oil and gas, EPC, and infrastructure projects across the UAE, Saudi Arabia, and the wider GCC. Our QRM Diploma programme equips professionals with the practical skills to build probabilistic calendar risk models that reflect real GCC construction conditions.

Learn more about the QRM Diploma →

Need to quantify calendar risk exposure on your GCC project? IQRM provides Safran Risk model builds, calendar risk calibration using local meteorological data, and QSRA consulting across the UAE and Saudi Arabia.

Contact us at info@iqrm.net to request a consultation →

Written by Rami Salem, Quantitative Risk Management specialist, 15+ years in oil & gas, EPC/EPCM, and infrastructure projects.

Establish Instructor’s Presence

Don’t forget that your initial postings in the discussion forum, your first messages sent to all by email, or the greeting you post on your course home page will do much to set the tone and expectations for your course....
Created with