P50: Meaning in Cost and Schedule Risk
P50 is the value with a 50% probability that the actual outcome will be at or below it. It is the median of the simulated results. A P50 finish date of 14 September 2028 means the project is as likely to finish before that date as after it. P50 is a coin-toss estimate, not a safe one.
How P50 is calculated
A Monte Carlo simulation runs the schedule or cost model thousands of times. P50 is the middle result once all iterations are sorted: half the outcomes are lower, half are higher.
Worked example
A refinery revamp has a deterministic Primavera P6 finish date of 30 June 2028. After a quantitative schedule risk analysis (QSRA), the illustrative results are:
| Measure | Finish date |
|---|---|
| Deterministic P6 date | 30 Jun 2028 (about P18) |
| P50 | 14 Sep 2028 |
| P80 | 20 Nov 2028 |
| P90 | 5 Jan 2029 |
The P6 date sits at roughly 18% confidence. Even the P50 is 11 weeks later. This is the usual pattern: a deterministic plan assumes nothing goes wrong, so it lands well below the median.
P50 is not the mean
Cost and schedule outcomes are skewed to the right: things can overrun by far more than they can underrun. That pulls the mean (the average) above the median. In the cost example on the P90 page, the P50 is $126m while the mean is closer to $127m. When a report says "expected cost", check whether it means the mean or the P50.
When to use P50
- Internal targets and forecasts that should be neither padded nor optimistic.
- Portfolio planning, where overruns on some projects offset underruns on others.
- Comparing options, where a like-for-like central estimate matters more than confidence.
Common mistakes
- Committing externally at P50. Half of all outcomes miss it. External commitments are normally made at P80.
- Calling the P50 the "most likely" value. The most likely value is the mode, which is usually lower than the P50 on a right-skewed curve.
- Assuming P50 equals the base estimate. A base estimate without risk usually sits well below P50.
Related terms
Frequently asked questions
- What does P50 mean?
- P50 is the median outcome of a risk simulation. There is a 50% chance the actual cost or duration will be at or below it and a 50% chance it will be higher.
- Is P50 the same as the average?
- No. P50 is the median. For right-skewed cost and schedule outcomes, the mean is usually higher than the P50.
- Why is my deterministic schedule below P50?
- A deterministic schedule assumes every activity goes to plan and no risk occurs. Once uncertainty and risk events are modelled, most plans land between P10 and P30.
Learn to build and defend these models
The QRM Professional Programme teaches QSRA, QCRA and Monte Carlo simulation on real project models in Safran Risk and Primavera Risk Analysis. CPD certified, UK and GCC.
IQRM is a specialist institute for Quantitative Risk Management, delivering Quantitative Schedule Risk Analysis (QSRA), Quantitative Cost Risk Analysis (QCRA) and Monte Carlo simulation training and consulting to major capital projects across the United Kingdom, Saudi Arabia and the UAE.
QRM Training
Consulting
Knowledge Hub
QSRA on UK Major Projects
United Kingdom
QSRA & QCRA training and consulting for UK infrastructure, nuclear and energy programmes.
QSRA Training UK
info@iqrm.net
United Arab Emirates
Rolex Tower, Sheikh Zayed Road, Dubai
+971 50 362 5784
QSRA Training UAE
Saudi Arabia
Riyadh delivery for giga-projects and Vision 2030 programmes.
QSRA Training Saudi Arabia
info@iqrm.net
Policy Pages
Get in touch

Copyright © 2026