Home / Glossary
IQRM Glossary

Quantitative Risk Management Glossary

Plain definitions of the terms used in quantitative schedule and cost risk analysis on capital projects. Each entry gives the meaning, a worked example with real numbers and the mistakes practitioners make, then links to a full guide.

C
Contingency

Contingency is the cost or time added to a project's base estimate or schedule to cover identified risks and estimating uncertainty within the agreed scope.

CorrelationGuide

Linking risks and activities that move together so the model does not understate total risk.

H
Heat map (risk matrix)Guide

A qualitative 5x5 rating grid, and why it cannot size contingency.

J
Joint Confidence Level (JCL)Guide

The probability of meeting cost and schedule targets together.

M
Merge Bias

Merge bias is the extra schedule risk created when several parallel paths converge on one activity or milestone.

Monte Carlo simulationGuide

Running a cost or schedule model thousands of times to get a distribution of outcomes.

P
P10

P10 is the value with a 10% probability that the actual outcome will be at or below it.

P50

P50 is the value with a 50% probability that the actual outcome will be at or below it.

P80

P80 is the value with an 80% probability that the actual outcome will be at or below it.

P90

P90 is the value with a 90% probability that the actual outcome will be at or below it.

Pre- and post-mitigationGuide

Comparing results before and after mitigation to value each response.

Primavera Risk AnalysisGuide

Oracle's schedule risk tool, formerly Pertmaster.

Probability distributionsGuide

Choosing triangular, PERT, uniform or other shapes for model inputs.

Q
QCRAGuide

Quantitative Cost Risk Analysis: Monte Carlo simulation of a cost estimate.

QSRA

QSRA (Quantitative Schedule Risk Analysis) is a Monte Carlo simulation of a project schedule.

Quantitative Risk Assessment (QRA)

Quantitative risk assessment (QRA) measures risk in numbers rather than labels.

Quantitative Risk Management (QRM)

Quantitative risk management (QRM) is the practice of managing project and business risk with numbers.

R
Risk Data Engine (RDE)Guide

IQRM's method for calibrating risk inputs from project data.

Risk mappingGuide

Linking register risks to the schedule activities they affect.

Risk registerGuide

The record of identified risks, owners, probabilities and impacts.

Risk statementGuide

Writing a risk as cause, event and effect so it can be quantified.

S
Safran Risk

Safran Risk is project risk analysis software from Safran Software Solutions.

Schedule contingencyGuide

Time held between the plan and the committed date, sized from a QSRA.

Schedule health checkGuide

Testing schedule logic and constraints before a risk analysis.

T
Three-Point Estimate

A three-point estimate describes an uncertain cost or duration with three values: optimistic (minimum), most likely, and pessimistic (maximum).

Tornado diagramGuide

The chart that ranks risks by their effect on the result.

Triangular Distribution

A triangular distribution is a probability distribution defined by three values: a minimum, a most likely value (the peak) and a maximum.

Turn the terms into capability

Knowing what P80 means is the start. Building a model that produces a defensible one is the skill.

Created with