Home / Glossary / QSRA
IQRM Glossary · Quantitative risk management

QSRA: Meaning of Quantitative Schedule Risk Analysis

QSRA (Quantitative Schedule Risk Analysis) is a Monte Carlo simulation of a project schedule. It applies duration uncertainty and risk events to the activities in a Primavera P6 or Microsoft Project schedule, then runs the network thousands of times. The result is the probability of finishing by any date, such as the P50 and P80, and the risks that drive the delay.

What QSRA tells you

  • Confidence dates: P50, P80 and P90 finish dates, instead of one deterministic date.
  • Schedule contingency: how much time is needed between the plan and the date you commit to.
  • Risk drivers: a tornado chart ranking the activities and risks that move the finish date most.
  • Mitigation value: how many weeks each mitigation buys, which tells you where to spend money.

The six steps

  1. Schedule health check

    Fix open ends, hard constraints and broken logic before any simulation.

  2. Uncertainty ranges

    Apply three-point estimates to durations, ideally calibrated from project data.

  3. Risk mapping

    Map discrete risk events from the risk register onto the activities they affect.

  4. Correlation

    Link activities that move together, so the model does not understate total risk.

  5. Monte Carlo simulation

    Run thousands of iterations in Safran Risk or Primavera Risk Analysis.

  6. Decision readout

    Report the P80 date, the drivers and the mitigations in terms a board can act on.

QSRA, SRA and QRSA

SRA (schedule risk analysis) is often used for the same thing; the Q stresses that the analysis is numerical. QRSA is a common misspelling of QSRA. QCRA is the cost equivalent, and the two combined give an integrated cost and schedule risk analysis.

Where QSRA is required

In the UK, major programmes use QSRA at funding and assurance gates, and NEC4 contracts put the programme at the centre of compensation events. In the GCC, owners on oil and gas, rail and giga-projects increasingly expect a QSRA before approving a baseline, with shutdown windows, LSTK terms and summer working limits modelled explicitly.

Common mistakes

  • Simulating a broken schedule. Poor logic gives a confident wrong answer.
  • Workshop guesses as inputs. Unchallenged three-point estimates are usually optimistic.
  • Ignoring merge bias. Parallel paths converging on one milestone delay the finish in ways the critical path does not show.

Related terms

Frequently asked questions

What does QSRA stand for?
QSRA stands for Quantitative Schedule Risk Analysis. It uses Monte Carlo simulation on a project schedule to forecast the probability of finishing by any date.
What is the difference between QSRA and QCRA?
QSRA analyses schedule risk and produces confidence dates. QCRA analyses cost risk and produces confidence budgets and contingency. Integrated analysis combines both.
What software is used for QSRA?
The most common tools are Safran Risk and Primavera Risk Analysis, working from a Primavera P6 or Microsoft Project schedule.

Need a defensible P80 on a live project?

IQRM runs independent QSRA and QCRA for owners, EPC contractors and PMCs across the UK and GCC, and turns the results into decisions a board can act on.

Created with