QSRA: Meaning of Quantitative Schedule Risk Analysis
QSRA (Quantitative Schedule Risk Analysis) is a Monte Carlo simulation of a project schedule. It applies duration uncertainty and risk events to the activities in a Primavera P6 or Microsoft Project schedule, then runs the network thousands of times. The result is the probability of finishing by any date, such as the P50 and P80, and the risks that drive the delay.
What QSRA tells you
- Confidence dates: P50, P80 and P90 finish dates, instead of one deterministic date.
- Schedule contingency: how much time is needed between the plan and the date you commit to.
- Risk drivers: a tornado chart ranking the activities and risks that move the finish date most.
- Mitigation value: how many weeks each mitigation buys, which tells you where to spend money.
The six steps
Schedule health check
Fix open ends, hard constraints and broken logic before any simulation.
Uncertainty ranges
Apply three-point estimates to durations, ideally calibrated from project data.
Risk mapping
Map discrete risk events from the risk register onto the activities they affect.
Correlation
Link activities that move together, so the model does not understate total risk.
Monte Carlo simulation
Run thousands of iterations in Safran Risk or Primavera Risk Analysis.
Decision readout
Report the P80 date, the drivers and the mitigations in terms a board can act on.
QSRA, SRA and QRSA
SRA (schedule risk analysis) is often used for the same thing; the Q stresses that the analysis is numerical. QRSA is a common misspelling of QSRA. QCRA is the cost equivalent, and the two combined give an integrated cost and schedule risk analysis.
Where QSRA is required
In the UK, major programmes use QSRA at funding and assurance gates, and NEC4 contracts put the programme at the centre of compensation events. In the GCC, owners on oil and gas, rail and giga-projects increasingly expect a QSRA before approving a baseline, with shutdown windows, LSTK terms and summer working limits modelled explicitly.
Common mistakes
- Simulating a broken schedule. Poor logic gives a confident wrong answer.
- Workshop guesses as inputs. Unchallenged three-point estimates are usually optimistic.
- Ignoring merge bias. Parallel paths converging on one milestone delay the finish in ways the critical path does not show.
Related terms
Frequently asked questions
- What does QSRA stand for?
- QSRA stands for Quantitative Schedule Risk Analysis. It uses Monte Carlo simulation on a project schedule to forecast the probability of finishing by any date.
- What is the difference between QSRA and QCRA?
- QSRA analyses schedule risk and produces confidence dates. QCRA analyses cost risk and produces confidence budgets and contingency. Integrated analysis combines both.
- What software is used for QSRA?
- The most common tools are Safran Risk and Primavera Risk Analysis, working from a Primavera P6 or Microsoft Project schedule.
Need a defensible P80 on a live project?
IQRM runs independent QSRA and QCRA for owners, EPC contractors and PMCs across the UK and GCC, and turns the results into decisions a board can act on.
IQRM is a specialist institute for Quantitative Risk Management, delivering Quantitative Schedule Risk Analysis (QSRA), Quantitative Cost Risk Analysis (QCRA) and Monte Carlo simulation training and consulting to major capital projects across the United Kingdom, Saudi Arabia and the UAE.
QRM Training
Consulting
Knowledge Hub
QSRA on UK Major Projects
United Kingdom
QSRA & QCRA training and consulting for UK infrastructure, nuclear and energy programmes.
QSRA Training UK
info@iqrm.net
United Arab Emirates
Rolex Tower, Sheikh Zayed Road, Dubai
+971 50 362 5784
QSRA Training UAE
Saudi Arabia
Riyadh delivery for giga-projects and Vision 2030 programmes.
QSRA Training Saudi Arabia
info@iqrm.net
Policy Pages
Get in touch

Copyright © 2026