Three-Point Estimate
A three-point estimate describes an uncertain cost or duration with three values: optimistic (minimum), most likely, and pessimistic (maximum). The three points define a distribution, usually triangular or PERT, that a Monte Carlo simulation samples from. Three-point estimates are the main input to QSRA and QCRA models.
The formulas
Triangular mean = (Min + Most likely + Max) / 3
Worked example
A pipeline tie-in is estimated at 20 days minimum, 25 days most likely and 40 days maximum.
- PERT mean = (20 + 100 + 40) / 6 = 26.7 days
- Triangular mean = (20 + 25 + 40) / 3 = 28.3 days
- Triangular P80 = 32.3 days, seven days more than the "most likely" figure a deterministic plan would use
The long right tail is why a plan built on most likely durations finishes late: each activity has more room to overrun than to underrun.
Why most three-point estimates are wrong
- Too narrow. Experts anchor on the most likely value and set a maximum only slightly above it. Real outcomes regularly fall outside workshop ranges.
- Absolute extremes are hard to judge. People estimate a P10 and P90 more reliably than a true minimum and maximum.
- Double counting with risk events. If the maximum already includes a discrete risk, and the same risk is in the register, it is counted twice.
Calibrating with data
The strongest three-point estimates come from evidence: productivity records, procurement lead times and performance on past projects. IQRM's Risk Data Engine (RDE) builds ranges this way, then tests workshop opinion against the data rather than taking it at face value.
Common mistakes
- Using a single percentage range such as -10% / +20% for every activity.
- Letting the planner who built the schedule set all the ranges.
- Ignoring correlation between activities that share a cause, such as the same crew or the same weather.
Related terms
Frequently asked questions
- What is a three-point estimate?
- It is an estimate made of a minimum, most likely and maximum value, which together define a probability distribution for a cost or duration.
- What is the three-point estimate formula?
- The PERT mean is (minimum + 4 x most likely + maximum) / 6. The triangular mean is (minimum + most likely + maximum) / 3.
- Should I use PERT or triangular?
- Triangular gives more weight to the tails and is more cautious when data is sparse. PERT concentrates results near the most likely value. Many practitioners use triangular unless data supports a tighter shape.
Replace guessed ranges with evidence
The Risk Data Engine builds three-point estimates from productivity, procurement and performance data, then tests workshop opinion against it.
IQRM is a specialist institute for Quantitative Risk Management, delivering Quantitative Schedule Risk Analysis (QSRA), Quantitative Cost Risk Analysis (QCRA) and Monte Carlo simulation training and consulting to major capital projects across the United Kingdom, Saudi Arabia and the UAE.
QRM Training
Consulting
Knowledge Hub
QSRA on UK Major Projects
United Kingdom
QSRA & QCRA training and consulting for UK infrastructure, nuclear and energy programmes.
QSRA Training UK
info@iqrm.net
United Arab Emirates
Rolex Tower, Sheikh Zayed Road, Dubai
+971 50 362 5784
QSRA Training UAE
Saudi Arabia
Riyadh delivery for giga-projects and Vision 2030 programmes.
QSRA Training Saudi Arabia
info@iqrm.net
Policy Pages
Get in touch

Copyright © 2026